Southland Industries
Articles
Video: What am I looking at?
Lauren Graham explains what you are looking at when you see the different parts of your chilled water system.
How engineers are imagining tomorrow
Engineers are critical for achieving progress and creating a better world for tomorrow.
Humidification installed for U.S. Army national museum
Southland and Envise installed an air system which provides controlled ventilation and humidification to gallery spaces.
Project Profile: Medical building with integrated project delivery
The project was significantly under budget and provided 11 percent savings overall.
Project Profile: Large-scale resort designed and consructed
M Resort is a full-service hotel, casino, and spa just south of Las Vegas Boulevard.
Project Profile: Building automation system in community hospital
The hospital successfully achieved LEED Gold certification.
Project Profile: Ultra-modern CityCenter tower
Aria Tower sits on 68-acres and serves as a centerpiece of the city’s downtown development
Utilizing mechanical and cultural training sessions to provide facility optimization
Tips on providing the maintenance and operations personnel and facility operators with the training and knowledge to help them become experts of the building automation system.
Carl R. Darnall Army Medical Center September update
The project is wrapping up with final check on the building pressure relationships and owner punch.
Carl R. Darnall Army Medical Center August update
Finishing up with commissioning and medical gas verification.
Carl R. Darnall Army Medical Center July update
Final phase of the project includes gas verification, owner punch, commissioning, and IBS punch.
Carl R. Darnall Army Medical Center June update
TAB for bed tower is being finished. Hospital level 3 punch list is in progress.
Carl R. Darnall Army Medical Center May update
Hospital level 2 is partially ready for furniture move-in. Hospital level 3 punch is underway.
Carl R. Darnall Army Medical Center April update
Hospital level 1 is ready for furniture move-in. Hospital level 2 punchlist is underway.
Carl R. Darnall Army Medical Center March update
South Clinic TAB is completed. Functional performance testing on the boiler system, water softener, and domestic water heat exchangers is underway.
Carl R. Darnall Army Medical Center January and February update
South Clinic TAB is completed. Functional performance testing on the boiler system, water softener, and domestic water heat exchangers is underway.
Carl R. Darnall Army Medical Center December update
Functional performance testing is being performed on the chilled water pumps, heating hot water pumps, heat recovery pumps, unit heaters, and domestic water booster pump skin in the central utility plant.
Carl R. Darnall Army Medical Center November update
Functional performance testings on the West Clinic and HVAC systems are underway. Finishes and punch lists at the North Clinic are substantially complete.
Carl R. Darnall Army Medical Center October update
Mechanical and plumbing systems are nearly completed on all buildings. Finishes are underway in all areas.
July 2 Southland Industries update: radiant floor tubing, test-and-balance
At the Carl R. Darnall Army Medical Center located in Fort Hood, Texas, Southland Industries has brought the chilled water and steam plants online, and test-and-balance has begun.
June 6 Southland Industries video update
Watch this video for an update on the engineering progress at the Carl R. Darnall Army Medical Center.
May 2 Southland Industries update: HVAC, plumbing in progress
At the Carl R. Darnall Army Medical Center located in Fort Hood, Texas, Southland Industries has begun commissioning HVAC systems, and radiant flooring tube is being installed.
April 4 Southland Industries update: Plumbing fixtures, chiller in progress
Southland Industries has completed several more steps at the Carl R. Darnall Army Medical Center located in Fort Hood, Texas.